HomeMy WebLinkAbout4C - Maintenance Center AGENDA NUMBER: PREP ARED BY: 4C PAUL HOKENESS, PARKS & RECREATION DIRECTOR CONSIDER APPROVAL OF FINAL CHANGE ORDER AND PAYMENT FOR MAINTENANCE CENTER APRIL 7, 1997 SUBJECT: DATE: INTRODUCTION: Rochon Corporation has submitted the final change order for the Maintenance Center as well as their final pay voucher. BACKGROUND: Final change order #4 represents a $500.00 price reduction for an incomplete punch list item. This item is for the repair of a birdbath (dip) in the blacktop in the back of the building. Staff has agreed that this is a minor issue and that our crew can make the repair in the Spring at a cost savings. The City retained $20,000.00 until Rochon completed all of our punch list items. Now that they have completed all of these items (with the exception of the dip in the blacktop) they have submitted their final payment request in the amount of $19,500.00. FINANCIAL IMP ACT: This change order and final payment will complete our contract with Rochon Corporation. Staff will be presenting a final budget report regarding the Maintenance Center and Salt/Sand storage building to the Council following the completion of the Salt/Sand storage building. Weare anticipating that this building will be completed later this Spring. AL TERNA TIVES: 1. Approve final change order #4 and authorize final payment for the Maintenance Center. 2. Table this Agenda item for a specific reason. 3. Deny this Agenda item for a specific reason. RECOMMENDATION: Staffrecornmends Alternative No.1. 162ff6iE'a.~~feek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245 AN EQUAL OPPORTUNIlY EMPLOYER ACTION REQUIRED: Motion and second to approve Change Order #4 and authorize ..fina1 paymce.n.>--jn the amount of $19,500.00 to ~hO]n,' rpor . on. / )\t i t/ / REVIEWED BY: AGCHG4.DOC CHANGE ORDER OWNER ARCHITECT CONTRACTOR FIELD OTHER [ ] [ ] [ ] [ ] [ ] SUBSTITUTE AlA DOCUMENTG701-1987 PROJECT: Prior Lake Maintenance Building (name, address) Prior Lake, MN CHANGE ORDER NUMBER: 4 DATE: 2/20/97 TO CONTRACTOR: (name, address) Rochon Corporation 12866 Hwy. 55 Plymouth, MN 55441 ARCHITECT'S PROJECT NO: CONTRACT DATE: September 19,1995 CONTRACT FOR: General Construction The Contract is changed as follows: Price reduction for incomplete punch list items. ($ 500.00) Not valid until signed by tbe Owner, Arcbitect and Contractor. The original (Contract Sum) was. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ Net change by previously authorized Change Orders. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ The (Contract Sum) prior to this Change Order was . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ The (Contract Sum) will be (decreased) by this Change Order in the amount of . . . .. ...... $ The new (Contract Sum) including this Change Order will be. . . . . . . . . . . . . . . . . . . . . . . . . . . $ 2,582,601.00 (18,933.00) 2,563,668.00 ( 500.00) 2,563,168.00 The Contract Time will be (increased) (decreased) (unchanged) by The date of Substantial Completion as of the date of this Change Order therefore is ( ) days. NOTE: This summary does not reflect changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have been authorized by Construction Change Directive. ~ddress PIVttf#f fA ::T -- ;Af7 City of Prior Lake OWNER 16200 Eai1e Creek Ave. S.E Address Prior Lake. MN 55372-1714 BRW Elness ARCHITECT Rochon Cor:poration CONTRACTOR BY DATE ~D CERTIFICATE FOR PAYMENT (SUBSmUTE AlA DOCUMENT G702) APPUCA 110N NO: PAGE ONE OF 2 PAGES 13 ...... ,. of Prior La.. 16200 Eagle Creek Ave. S.E. Prior Lake, MN 553n PROJECT: Prior La.. Public ~. Feclllty 17073 Adelmann Stree! Pnor Lake, Minnesota 31-Aug-96 VIA (ARCHITECT): BRW E1n_ 700 3rd St. So. Minneapolis, MN 55415 ~.':- .~...:.~::::.-:.<~,:.;':~. :),' ~r~;~Y"~~~:, :.".. '".:-; ~''''-: ~.~/ . ..", CONTRACT FOR: General ConstnlcUon CONTRACTOR'S APPUCATlON FOR PAYMENT CHANGE ORDER SUMMARY Change Orders approved in ADDITIONS DEDUCTIONS previous monIhs by 0Nner TOTAL 14,179.00 25,886.00 Approved this Month Number Date Approved V 3 August 28, 1996 7,226.00 4 February 20, 1997 C 500.00 TOTALS 14,179.00 33,612.00 Net change by Change Orders (19,433.00) The undersigned Contractor certifies that to the best of the Contractor's knowledge, infonnation and belief the Wort< covered by this Application for Payment has been completed in accordance with the Contract Documents, that all amounts ha\Ie been paid by the Contractor for Wort< for which previous Certificates for Payment _re i1lsued and payments received from the Owner, and that current payment shown herein is now due. By: Date: March 1, 1997 . . I~":-: CANDYCE LEE SARTELL I '~r!.' NOTARY PUBLIC - MINNESOTA . ,-.' My Comm. Expires Jan. 31, 2000 . . PERIOD TO: ARCHITECT"S PROJECT NO: 2908.Zoo CONTRACT DATE: September 19th, 1995 Application is made for Payment, as shown below, in connection with the Contract, Continuation Sheet, Substitute AlA Document G703 is attached. 1. ORIGINAL CONTRACT SUM.................................. $ 2 Net Change by Change Orders................................ $ 3. CONTRACT SUM TO DATE (Une 1+/-2)................. $ 4. TOTAL COMPLET'ED & STORED TO DATE........... $ (Column G on G703) 5. RETAINAGE: a._% of Completed Wort< (Column D+E on G703) b._% of Stored Matenal (Column F on G703) Total Retainage (Une 5a+5b or Total in Column I of G703).............................. $ 6. TOTAL EARNED LESS RETAINAGE...................... $ (Une 4 less Line 5 Total) 7. LESS PREVIOUS CERTIFICATES FOR PAYMENT (Line 6 from pnor Certificate)......... $ 8. CURRENT PAYMENT DUE..................................... $ 9. BALANCE TO FINISH, PLUS RETAINAGE.............. $ (Line 3 less Line 6) State of: Minnesota County of: Hennepin LJ 2..C::l- '7clJSS - SC 1 :::OO[k::~~.:.,~3:'~ My Commission expires: January 3~ 2,582,601.00 (19,433.00) 2,563,168.00 2,563,168.00 0.00 2,563,168.00 2,543,668.00 19,500.00 0.00 ARCHITECT"$ CERTIFICATE FOR PAYMENT In accordance with the Contract Documents, based on on-site observations and the d8tlI comprising the above applic8liOn, the Architect c:ertiIles to the Owner that to the best IX the Architect's knowledge, infamation and belief the Work has progressed as indicated, the quality of the Work is in accordance with tile Contract Documents, and the Contractor is entitled to payment IX the AMOUNT CERTIFIED. ::k~~~ Paul HokenesS Park & RecreatiOn Director Date: 3 }J2> L4,) AMOUNT CERTlFlED._.._...._...._......._.S It .fZJ d (Attach explanation If amount certified differs from the amount applied for.) Date: negotiable. The AMOUNT is payable only named herein. Issuance, payment and acceQtance c:A payment are without prejudice to any rights of the Owner or Contractor under this Contract. By: /~~: ~t3lctl Ralph Teschner Finanace Director --....,.~