HomeMy WebLinkAbout7C -Ponds Park Field Lighting
DA TE:
7C
PAUL HOKENESS, PARKS & RECREATION
DIRECTOR
CONSIDER APPROVAL OF REJECTION OF BIDS
FOR ATHLETIC FIELD LIGHTING AT THE POND'S
AND AUTHORIZE THE REBIDDING OF THE
PROJECT
JUL Y 21, 1997
AGENDA NUMBER:
PREPARED BY:
SUBJECT:
INTRODUCTION:
The purpose is to authorize the rejection of bids for athletic
field lighting at the Pond's Park and authorize the rebidding
of the project.
BACKGROUND:
The Council authorized bidding of this project at the April 7,
1997 meeting. On Tuesday, June 24th the city accepted bids
for this project and at 10:00 a.m. the bids were opened and
recorded.
Recognizing that the Pond's is adjacent to two eXIstmg
neighborhoods the Parks Advisory Committee conducted a
public meeting to discuss the proposed lighting project. The
residents raised two concerns: 1. That security lighting is
needed within the park, and 2. That the field lights would
spill into their yards and shine into their windows.
Accordingly staff determined that the Musco lighting system
had an effective system which could address these residential
concerns as well as direct the lights onto the field. Therefore,
the City's electrical engineering consultant used Musco, or
equivalent as the basis for preparing the specifications for the
project. The specifications were written to allow other
vendors to bid their products, provided they identify their
exceptions to the lighqng engineer.
There were only two bids for this project. The highest bid
was $417,388.00. The lowest bid was $332,000.00. Both
contractors who bid the project proposed the use of Musco
Lighting.
DISCUSSION:
Nine contractors picked up plans and originally showed
162~~~efeek Ave. S.E., Prior Lake. Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL OPPORTtiNITY E.;"1PLOYER
interest in the project. The electrical engineer hired by the
City to design the lighting system and assist with
specifications advised us that with a specialized project such
as this it is typical not to have a lot of bidders. However, he
felt that we should be able to attract a few more if the City
rebid and scheduled the work in the Fall. Staff found that
summer is a very busy time of year for most electrical
contractors and many are working on school projects. The
electrical engineer believed we would have more competitive
bids in the Fall.
We were advised by one of the equipment suppliers (not a
commercial electrical contractor) that they had not seen the
bid advertisement in the Construction Bulletin or Dodge
Reports and that they didn't have enough time to provide
specifications to the electrical contractors that were bidding
the project. Although this lighting supplier is not an electrical
contractor and would not be bidding the project they
questioned our bidding process and were concerned that they
would not be able to supply the lights and poles. The City
received a letter from an attorney expressing concerns and
alleging improper bidding procedures. We have included a
copy of the attorney's letter as well as a copy of the City
Attorney's response.
FISCAL IMPACT:
The estimates for this project were approximately
$300,000.00 for the field lighting. At the neighborhood
meeting the neighbors suggested security lighting also be
included. The P.A.c. and staff felt that this would be an
excellent opportunity to add security lighting in the park
since we could utilize the same contractor, trenches, poles,
and conduits to install this additional security lighting. The
estimates for this additional lighting were $20,000.00
bringing the total estimate to $320,000.00. The electrical
engineer feels that we should be able to get closer to or under
this amount if we rebid the project.
Funding for this project is included in the 1997 Parks and
Library Referendum.
ALTERNATIVES:
1. Authorize the rejection of all bids for athletic field
and security lighting at Pond's Park and authorize
the rebidding of the project.
2. Table this item for a specific reason.
LlTEBID.DOC
RECOMMENDATION:
ACTION REQUIRED:
REVIEWED BY:
Attachments
LITEB lD .DOC
Staff recommends Alternative #1 which would allow us to
rebid the project.
CAMPBELL KNUTSON
Pwfessic1nall\.~~' H.': i~l tic In
j\(tOITlcys dt Llw
. . .
J,,<.:I.1 ):lIl1ntk
A ndr..:" Md )lhv"ll Pl ":,Ill,,,.
iYl:Hrh,:w K. I~rl)kl'
J"i..n F. Kc.:lly
M:lrrh,:w I. h ,II
Molr!.:! I,Tl(,' ~\. 1vIcC~,\ITIII1
Gt.:l1rl!" T. Srl:rlll:n~"n
Tl\1l111:" J. Cdllll'l,dl
Rllg!:'1' N, KI1L1(~l'l1
Th'lnl;JS M, S,'.llrr
J","", R, W"btl.,n
Fllhlrr R. Knl:r,ch
SU"'dll L",,, p"<.:,,
(612) 4Sl-50CO
F~-LX (612) 452-5550
Writer' 5 Extension: 226
Writer's Fax: 452-5550
.,,\l.v.liUIL.,~J in \.1/i."I:,m.\Jn
I.I{C"IIIJ>od.
(;011"'1 l.. Fu-=h,;
July 15, 1997
Mr. Thomas L. Fabel, Esq.
Linquist & Vennum, P.L.L.P.
4200 IDS Center
80 South Eighth Street
Minneapolis, Minnesota 55402-2205
Via Fax #371-3207
and U.S. Mail
RE: City of Prior Lake
Ponds Athletic Field Lighting Project
Dear Mr. Fabel:
Your letter to me dated July 1, 1997 concerning the City's bid solicitation in connection with
the Ponds athletic field lighting project alleges (1) irregularities in the procedure used to bid the lighting
equipment and (2) improprieties concerning certain companies obtaining "the inside tract." These are
very serious allegations, but absolutely unfounded. Generally, I am reluctant to respond to letters from
attorneys who fail to identify who they are representing, particularly in a case such as this which I
suspect involves a disgruntled equipment supplier who failed to have their equipment pre-qualified.
This letter will address your client's allegations in the order set forth in your July 1, 1997 letter.
Minnesota Statutes Chapter 429, which you cite in your letter. does not apply to this project. Minnesota
Starotes Chapter 429 applies to projects that intends to specially assess. The installation of athletic field
lighting at Ponds Park is not being paid for through the use of special assessments. The City followed
the proper procedure as required by Minnesota Statutes Section 471.345. the applicable statute.
Your second allegation. asserted on behalf of your unnamed client, states that an equipment
manufacturer, MUSCO, had somehow gained "an inside track on the Prior Lake project." Attached
is a copy of the draft staff report for the Prior Lake City Council's July 21, 1997 meeting. I would not
be surprised if the equipment supplier described in Mr. Hokeness's staff report and your client turned
out to be the same individual. The staff report is self explanatory.
SUttL: 317 . EaganJ<llt' Offic~ C~nc~r · 1380 C:orflorare Cenr~r Curve · t:.1C;111. \.-1 N 551 21
T. Fabel
July 15, 1997
PalZC 2 of 2
Mr. Hokcness, City Parks and Recreation Director, following the advise of the electrical
engineering firm that consulted with the City on this project, is seeking authority from the City Council
to reject all bids and authority to re-bid the project in the fall. Following applicable statutory
requirements, when the project is re-bid, it will again be advertised in the Construction Bulletin and
Dodge Report.
Very truly yours,
CAMPBELL KNUTSON
Professional Association
By:
~~ ~~'A
/ Suesan Lea Pace
Prior Lake City Attorney
SLP:kgm
cc: Mayor and City Council
Frank Boyles, City Manager
Paul Hokeness, Director of ParkslRec
LINDQUIST & VENNUM P.LL.P.
4200 IDS CcNTVI
80 SouTH ElGtm4 5nuT
~. MINecm 5S402-2205
TELEPHONI:612-371-3211
F.x:612-371-3207
IN ClENvol
l..JNoal.wr, V!Mu.l & ~ ~.l.LP.
600 17TH 5TMrT. Sum 2125
0INvu.. Col.oIlAoo 80202-5401
TELEPHONI:303-573-5900
ATTORNEYS AT LAW
Thomas L. Fabel
(612) 371-3546
July 1, 1997
SENT BY FACSIMILE AND U.S. MAIL
Suesan Lea Pace, Esq.
CAMPBELL KNUTSON SCOTT & FUCHS
EagClnda!e Office C enter, Suit~ 317
1380 Corporate Center Curve
Eagan, Minnesota 55121
Re: City of Prior Lake Contract for
Ponds Park Athletic Field Lighting: Bid Protest
Dear Ms. Pace:
I am writing to advise you of irregularities in the competitive bid-letting process
for the above project and to seek your assistance in obtaining voluntary correction of
these irregularities.
I have been advised by our client that this project was first advertised for bids on
June 6, 1997, and that the final day for bid submission and bid opening occurred on
June 24, 1997. The low bid for the project, which includes all materials and labor, was
approximately $330,000. The materials component for projects of this sort is normally
50-55% of the project price, which here would be approximately $165,000 - $175,000.
City council consideration of the bid for possible contract award is scheduled for July 7,
1997. We do not know whether City staff has recommended a contract award, but we
have been advised that the lowest bid substantially exceeds the budgeted amount for
this project.
The apparent irregularities in the bid-letting process involve (1) the timeliness of
the published notice for bid submission and (2) the published specifications for the
included lighting materials. I will address these subjects separately.
LT01:433~81_1
LINDQUIST & VENNUM P.LL?
July I, 1997
Page 2
TIMELINESS OF NOTIFICATION
The mandatory procedures for the solicitation of bids by the City of Prior Lake for
this project are set forth in Minn. Stat. 9429.041. That statute provides that for projects
with estimated costs exceeding $100,000, the published advertisement for bids must
occur no less than three weeks before the last day for bid submission. The only
published advertisement for this project known to our client appears in the Friday, June
6, 1997 edition of Construction Bulletin Magazine, which was received by our client on
June 10. However, even if June 6 is considered the effective date of publication, the
earliest permissible date for the closure of bids was June 27, which was three days
after the bid opening for this project.
It deserves note that this was no mere technical deficiency. As a practical
matter the shortness of the notice period effectively precluded any supplier of lighting
materials, other than one with an inside track, from receiving fair consideration for its
materials. The uinside track" problem I will address later in this letter. For present
purposes it is enough to note that the City engineer for this project, Wunderlich-Malec
Engineering, required all potential materials suppliers to submit for engineering review
the specifications on their products at least ten days before the bid opening. Since
these submissions are complicated documents requiring several days for assembly and
review, this ten-day requirement could not be met by any materials supplier which was
not working on the project prior to the publiShed advertisement for bids.
The shortness of time allowed by the City for the submission of bids is one
reason why just one supplier of materials - the Musco Sports Lighting Company of
Muscatine, Iowa - is included in any of the bids received by the City. Certainly the
appearance of just one supplier for materials in a project of this magnitude should be a
very significant concern for the City. That concern should be greatly exacerbated by
the additional possible irregularity in this process, which is that the materials
specifications all but assured that Musco would be the supplier.
LIGHTING MATERIALS SPECIFICATIONS
In one ,of many efforts to insure the benefit of competition in public procurement,
Minnesota law generally requires generic specifications in bid solicitations for the
purchase of supplies and equipment. Minn. Stat. 9471.35 provides as follows:
When any county, city, town, or school district calls for bids for the
purchase of supplies or equipment, specifications shall not be so
LTOl:433$81_1
LINDQUIST & VENNU~t P.LLP.
July 1, 1997
Page 3
prepared as to exclude all but one type or kind but shall include
competitive supplies and equipment.
Violation of this provision constitutes a gross misdemeanor. Minn. Stat. 9471.37.
It is the opinion of our client, a supplier of lighting equipment of the type needed
for this project, that the specifications for this bid violate 9471.35, or at least the spirit
of that statute. This conclusion may not be apparent from the specifications on their
face, but the structure of the specifications and the extent of their detail very c1ear!y
favor Musco as the supplier, This fact gives rise at least to the appearance that Musco
obtained an inside track on this project, which facilitated its ability to be the only
available supplier for materials.
This possibility that Musco somehow obtained an inside track on the Prior Lake
project is supported by a pattern involving many similar projects in the Twin Cities
metropolitan area. Time and again in sports lighting projects, Wunderlich-Malec has
been designated as the city engineer for the project, and Musco has been the supplier
of all lighting equipment. Indeed, our client is not aware of a single sports lighting
project in recent history where Wunderlich-Malec has served as engineer and where
Musco has not been the successful supplier of materials. We believe that this history,
coupled with the unusual nature of the specifications for this project, coupled with the
fact that the bid solicitation was not advertised for the required period, and coupled with
the fact that the low bid substantially exceeded budget, all should create great concern
for the City of Prior Lake and its taxpayers.
Our client is a supplier of high-quality, reasonably priced, athletic field lighting
materials. Its products and the products of other suppliers should be available for
consideration by the City of Prior Lake in any project of this magnitude. However, that
will happen only if the City now calls for new bids on this project, and then proceeds as
required by law, both as to the timing of the advertisement and as to the nature of the
specifications.
Please bring this matter to the attention of the Prior Lake mayor and city council
at your very earliest opportunity. Obviously, there is little time for the statutory
irregularities to be recognized and rectified. As you know, injunctive relief is available
to assure compliance with these statutes, but we feel confident that the City would
prefer to correct this situation without the need for judicial involvement.
LTOl:433~81_1
LINDQUIST & VENNUM P.L.LP.
July 1, 1997
Page 4
Thank you very much for your prompt attention to this matter.
TLFlles
cc: Mr. Paul Hokeness
LTOl:4JJ.581_1
~tJ-~