HomeMy WebLinkAbout 8A Cates Area Public Hearing Presentation2017 Street Reconstruction Project –
Cates Street Area Improvements
Cates Street, Albany Avenue, CJ Circle, Five Hawks Avenue, Park
Avenue
January 9, 2017
Public Improvement Hearing
Agenda
•Project Objectives
•Project Area
•Existing Conditions/Proposed
Improvements
•Review Methods
•Estimated Project Costs
•Estimated Preliminary
Assessments
•Special Assessment Process (MN
Statutes Chapter 429)
•Preliminary Project Schedule
•Project Feedback
•Next Steps
Project Objectives
•Reconstruct Deteriorated Streets
•Upgrade City Underground Utilities
•Sanitary Sewer
•Watermain
•Storm Sewer
Project Area
Street Improvements
Street Improvements
•Two Improvement Methods
•Reclaim
•Reconstruct
Street Improvements
(Method 1 -Reconstruction)
•Cates Street, Albany Avenue, CJ Circle and Five Hawks Avenue
•Existing bituminous streets with little concrete curb and gutter
•Albany Avenue -proposed 28’ width (26’ existing width) with B618
concrete curb & gutter
•All other streets -proposed 30’ width (30’-32’ existing width) with
B618 concrete curb & gutter
•7-ton design street section
•4” Bituminous
•8” Aggregate Base
•12” Granular Material
•Turnaround proposed at the end of Five Hawks Avenue
•Remove the roadway east of Albany Avenue on Cates Street
Street Improvements
(Method 2 –Reclamation)
Park Avenue
•Existing 26’ width with surmountable concrete curb & gutter
•Existing concrete curb and gutter to remain in place (spot
repairs)
•7-ton design street section
•4” Bituminous
•8” Reclaim Material
What’s Under My Street
Utility Improvements -Reconstruct Area
Proposed Utility Improvements –Reconstruct Area
•Sanitary Sewer: Replace 8” VCP with 8” PVC
•Water Main: Replace existing with 8” PVC
•Storm Sewer: Replace existing pipes and
catch basins
Utility Improvements –Park Avenue
Proposed Utility Improvements –Park Avenue (Reclaim)
•Sanitary Sewer: No pipe replacement
•Water Main: Replace valves and hydrants
•Storm Sewer: No existing storm sewer
Estimated Project Costs
(Reconstruction)
Estimated Project Costs and Financing (Reconstruction)
ITEM ESTIMATED PROJECT COSTS ASSESSMENTS CITY SHARE
Streets $995,150 $398,060 $597,090
Sanitary Sewer $229,180 $229,180
Watermain $371,180 $371,180
Storm Sewer1 $62,960 $17,184 $45,776
Total $1,658,470 $415,244 $1,243,226
1 Includes $20,000 in Water Quality Improvements that are not assessable
Estimated Project Costs
(Reclamation)
Estimated Project Costs and Financing (Reclamation)
ITEM ESTIMATED PROJECT COSTS ASSESSMENTS CITY SHARE
Streets $192,530 $77,012 $115,518
Sanitary Sewer $1,320 $1,320
Watermain $24,240 $24,240
Total $218,090 $77,012 $141,078
Total Project Cost
ITEM RECONSTRUCTION AREA RECLAMATION AREA TOTAL
Ad Valorem (Property Taxes)$597,090 $115,518 $712,608
Assessments (40%)$415,244 $77,012 $492,256
Utility Fund -Sewer $229,180 $1,320 $230,500
Utility Fund -Water $371,180 $24,240 $395,420
Water Quality Fund $45,776 $0 $45,776
Assessment Roll (Per Unit) Reconstruction $6,106.53
Assessment Roll (Per Unit) Reclamation $4,477.44
Total $1,658,470 $218,090 $1,876,560
Estimated Project Costs
Estimated Assessments
•MN State Statute Chapter 429 Requires Assessment to be a minimum
of 20% of Bonding Amount
•Street and Storm Assessment 10 Year Period
•Assessment Rate 2% greater than Project Bond Rate (2015 Rate
4.44%)
Reconstruction Reclamation
Assessment (40%)
Street & Storm $415,244 $77,012
Assessment –Unit Method
Assessable Units -Reconstruction 68 Units
Assessable Units –Reclamation 17.2 Units
Estimated Unit Assessment –
Reconstruction $6,106.53/Unit
Estimated Unit Assessment –
Reclamation $4,477.44/Unit
Assessment Map
Assessment Review Workgroup
•Met on November 16, 2016
•Reviewed the Assessment Map
•Reviewed the Estimated Project Cost
•Reviewed the Unit Method of Assessment
•Discussed the Combination of the Assessments
•Reviewed the Estimated Assessment Amount
Public Improvement Process
Preliminary Project Schedule
ACTIVITY DATE
Held First Informational Meeting October 19, 2016
Accept Feasibility Report / Call for Public Hearing November 28, 2016
Second Informational Meeting December 14, 2016
Conduct Public Hearing/Order Project January 9, 2017
Third Informational Meeting March 2017
Approve Plans and Specifications / Order Advertisement for Bids March 2017
Open Bids April 2017
Accept Bids/Award Contract May 2017
Begin Construction Late May 2017
Complete Base Course of Bituminous Pavement October 2017
Authorize Amount to be Assessed/Schedule Assessment Hearing October 2017
Conduct Assessment Hearing/Adopt Assessment Roll October 2017
Project Feedback
Informational Meeting
•Held October 19, 2016
•Approx. 18 property owners in attendance
•Introduction to the project
•Discussed typical project, process, and timeline
Project Questionnaire
•17 questionnaires filled out and turned into City
•Concerns expressed about sidewalk installation
•Concerns expressed about ponding at Cates and in driveways
•Interests in more street lighting
Council Actions
•City Council Meeting on November 28, 2016
•Passed a Resolution
•Accepted Feasibility Report
•Called for Public Hearing on January 9, 2017
•Directed City Staff to Evaluate the Following Items:
•Remove Roadway East of Albany Ave on Cates St
•Eliminate Turnaround at end of Five Hawks Ave
•Review Addition of Trail or Sidewalk Through Neighborhood
•Park Ave Pavement Section and Width
•Addition of Storm Sewer to Park Ave
Project Feedback
Neighborhood Meeting
•Held December 14, 2016
•Discussed Feasibility Report
•Discussed project, process, and timeline
•Concerns expressed about sidewalk/trail installation
Council Directives
Remove Roadway East of Albany Avenue on Cates Street
•City Staff agrees
•Proposed the removal as part of the Feasibility Report
Council Directives
Eliminate Turnaround at South End of Five Hawks Avenue
•City Staff Recommends Turnaround
•Estimated Project Cost ~$24,000
Council Directives
Review Trail or Sidewalk Through Neighborhood
•Five Hawks Elementary to St. Michaels Church
Council Directives
•Staff Recommends Not to Construct
•Estimated Project Cost ~$290,000
Council Directives
Park Avenue
•Street Width
•Pavement Section
•Storm Sewer
Council Directives
Park Avenue -Street Width
•Existing 26’ street width with concrete curb and gutter
•Existing width does not allow for parking on both sides
•Pleasant Street, Park Avenue, and Green Heights Trail appear
to serve as neighborhood throughway
•If a wider roadway is desired, recommend project is changed
from a reclamation to a reconstruction project
•Reconstruction project increases project costs from $192,530
to $334,000 (+$141,470)
Council Directives
Park Avenue –Pavement Section
•Proposed pavement section meets a 7-ton design roadway
which is typical for a local street
•If a higher factor of safety is desired, recommend increasing
gravel section from 8” to 12”. Estimated project cost increase
of $15,480
•If a sand section is desired, recommend project is changed
from a reclamation to a reconstruction project
Council Directives
Park Avenue –Storm Sewer
•No storm sewer exists on Park Avenue
•Only drainage issue the City is aware of is at the intersection
of Park Ave and Cates St
•Drainage issue can be fixed without storm sewer
•Based on drainage area, storm sewer should be added to the
street
•Storm Sewer is feasible from 2 locations
•Extend from Five Hawks Ave ($60,430)
•Extend from Dutch Ave –reclaim project ($76,620)
•Extend from Dutch Ave –reconstruction project ($50,000)
Council Directives
Park Avenue –Storm Sewer Options
Council Directives
Park Avenue Recommendations
•If Project Remains a Reclamation Project:
•Keep existing width
•Keep pavement section as proposed (8” gravel)
•Do not extend storm sewer
•If Project Changes to a Reconstruction Project:
•Delay construction until 2018
•Further evaluate street width, pavement section, and
storm sewer needs
•Less impacts to the neighborhoods with construction of
Park Avenue and Green Heights Trail during the same
year
Next Steps
•City Council Initial Questions
•Open Public Hearing
•End Public Testimony
•Answer Questions from the Pubic Hearing
•City Council Discussion
•Consider Approval of a Resolution Ordering the Project with
Direction on Specific Elements of the Project
City Council Direction Needed
•Direction on the Addition of Sidewalk and Trails
•Direction on Turnaround for Five Hawks Avenue
•Direction on Park Avenue Storm Sewer
•Direction on Park Avenue Street Width and Inclusion in 2017
Project as a Reclamation Project
•Other Direction Based on Public Testimony
Questions/Comments