HomeMy WebLinkAbout05(C) - Resolution Approving a Work Order for Engineering Services for the Water Treatment Plant Filter Media Replacement Project (2023-08) ReportPage 1 of 2 Public Works Consultant Pool Work Order Water Treatment Plant Filter Media Replacement (2023-08) WSB & ASSOCIATES, INCORPORATED, dba WSB This work order (“Work Order”) is issued on this 14th day of January, 2025 by the City of Prior Lake (“City”) pursuant to the Public Works Consultant Pool – Master Agreement dated April 20, 2020 (“Contract”) between the City and WSB & Associates, Incorporated, dba WSB (“Consultant”). Based on the mutual promises and covenants set forth herein, the sufficiency of which are hereby acknowledged, the City and Consultant agree as follows: 1. Scope of Work Order. Consultant agrees to provide, perform and complete all the services requested by the City in this Work Order and attached Exhibit 1 (“Work”), which Work shall be subject to the terms and conditions of this Work Order and the Contract. 2. Term of Work Order. All Work requested by this Work Order shall be completed by December 31, 2026. 3. Compensation for Work Order. City agrees to pay the Consultant an hourly, not-to- exceed sum of $46,760. 4. Consultant Representative. Consultant has designated Steve Nelson to manage the Work Order subject to the supervision of Consultant’s representative. ISSUED BY CITY OF PRIOR LAKE ___________________________________ Mayor ___________________________________ City Manager RECEIVED AND ACCEPTED BY WSB & ASSOCIATES, INC. _____________________________________ Signature ____________________________________ Title Page 2 of 2 Exhibit 1 – Scope of Work Order 1 7 8 E 9 T H S T R E E T | S U I T E 2 0 0 | S A I N T P A U L , M N | 5 5 1 0 1 | 6 5 1 . 2 8 6 . 8 4 5 0 | W S B E N G . C O M November 27, 2024 Nick Monserud, PE City of Prior Lake 4646 Dakota Street SE Prior Lake, MN 55372 Re: Proposal for Engineering Services Water Treatment Plant (WTP) - Filter Media Replacement Prior Lake, Minnesota Dear Mr. Monserud: WSB appreciates the opportunity to submit this letter proposal for performing engineering services for the replacement of the filter media in Prior Lake’s Water Treatment Plant (WTP). Engineering Services Goal: Prior Lake’s goal for this project is to successfully replace the filter media in all six (6) of the WTP’s Filters - with the work divided into two separate construction years, as outlined below. A. 2025 – Filter Media Replacement ·Filters No. 4, 5, and 6 B. 2026 – Filter Media Replacement Filters No. 1, 2, and 3 Following each year’s filter media removal, Prior Lake would like the condition of the existing underdrain system assessed, to ensure that it can remain in place and that the new filter media can be placed over the existing underdrain block. Exclusions Items and work tasks NOT included in the scope of services provided by WSB include: 1) Survey services. 2) Geotechnical services. 3) Permitting. (No construction permit required for maintenance-related work.) 4) Analysis of, and modification to, the existing water distribution system. 5) Change to Filter Backwash or Chemical Feed Programming 6) Evaluation of media tendency to avoid becoming coated with new treatment (bypassing the aerator and orthophosphate feed location, etc.). a.Note – these services will be provided separately, as filter evaluation services, on an hourly rate basis as requested by Prior Lake 7) Any work, beyond inspection, associated with replacing the existing underdrain block and system. EXHIBIT 1 Nick Monserud Letter Proposal – WTP Filter Media Replacement November 27, 2024 Page 2 Scope of Work: The proposed scope of work includes “Phase 1” through “Phase 4”, outlined below. 1: Preliminary Design Phase WSB will take the lead on preliminary design coordination and communication and prepare visual tools and reference materials for the kick-off meeting. The proposed work will include one (1) meeting with City staff; some WSB participants may attend the meeting virtually. 2: Final Design Phase WSB staff will prepare plans, specifications, and bidding requirements for the 2025 and 2026 Filter Media Replacements. · Minimum Contractor Qualifications - will be specified to ensure a qualified contractor is retained for the work. · Sequence of Construction and Project Phasing – will be called out so as to ensure the contractors understand the coordination with and accommodation of the water plant operator’s needs for an operating water treatment plant throughout the project duration. . · Limits of Work - Will be detailed to ensure the contractor’s assessment of the site and the pre-existing conditions and constraints associated with the work. 3: Bidding Services Phase WSB will lead the bidding services listed below. · One Mandatory Pre-Bid Meeting - will be needed to accommodate the contractor’s assessment of the site and the pre-existing conditions and constraints associated with the work. Nick Monserud Letter Proposal – WTP Filter Media Replacement November 27, 2024 Page 3 4: Construction Administration & Inspection Services Phase WSB will lead construction related services listed below. Schedule WSB will work with Prior Lake to establish a schedule that works for the City. We anticipate that the majority of WSB’s design work could be completed within 16 weeks of notice to proceed. In total, WSB anticipates that the final project manual will be available within 18 weeks of the notice to proceed. Nick Monserud Letter Proposal – WTP Filter Media Replacement November 27, 2024 Page 4 Fees WSB will complete the proposed scope of work for an hourly, not-to-exceed fee of $46,760. The estimated fee breakdown by task is shown in the attached “Proposed Estimate of Hours and Fees.” If you are in agreement with the scope of services, please sign this letter and return a copy to WSB. Our receipt of an executed copy will be WSB’s notice to proceed. If you have any questions about this proposal, please feel free to call me at 612.258.8152. Sincerely, WSB Steve Nelson, PE Director, Water/Wastewater 612-258-8152 ACCEPTED BY: City of Prior Lake Name ______________________________ Title ______________________________ Date ______________________________ Pr o j e c t M a n a g e r (S t e v e N e l s o n ) P r o c e s s E n g i n e e r (M i c h a e l B o u r l a n d ) Pr o c e s s D e s i g n e r (W i l l S c o f i e l d ) A d m i n . T e c h n i c i a n ( K a r l a P e d e r s o n ) Total Hours Fee 1 PRELIMINARY DESIGN PHASE 1.1 Water Plant Filter Access Assessment 4.0 4 $1,056 1.2 Facilitate Staff Decisions on Work Area Limits and Protection 2.0 8.0 10 $1,592 Task 1 - Total WSB Staff Estimated Hours and Total Phase Fee 6.00 0.00 8.00 0.00 14 $2,648 2 FINAL DESIGN PHASE 2.1 Plans & Specifications 6.0 15.0 30.0 4.0 55 $9,024 Task 2 - Total WSB Staff Estimated Hours and Total Phase Fee 6.0 15.0 30.0 4.0 55 $9,024 3 BIDDING SERVICES PHASE 3.1 Post project manual on Quest CDN, or approved bidding site 1.0 1 $135 3.2 Hold Pre-bid Meeting 6.0 6 $1,164 3.3 Respond to bidder inquiries 1.0 1.0 2 $327 3.4 Issue addenda 2.0 3.0 1.0 6 $922 3.5 Open bids 1.0 0.5 2 $262 3.6 Check the low bidder qualifications/references 0.5 1 $67 3.7 Analyze bids and bid alternatives 0.5 0.5 1 $134 3.8 Submit letter of recommendation for award 1.0 0.5 2 $201 3.9 Prepare Notice of Award and Contract agreement for Contractor 1.0 1 $135 Task 3 - Total WSB Staff Estimated Hours and Total Phase Fee 0.0 10.0 6.0 4.5 21 $3,346 4 CONSTRUCTION ADMINISTRATION & INSPECTION SERVICES PHASE 4.1 Furnish complete plan sets, hard copy (3), and any required revisions to the contractor for building permit approval.2.0 4.0 6 $830 4.2 Coordinate, facilitate, and participate in periodic meetings with the contractor, subcontractors, suppliers and City staff.12.0 8.0 10.0 30 $6,234 4.3 Review and approve contract submittals / shop drawings. 3.0 3 $411 4.4 Review/approve/deny proposed changes to the plans and specifications; document with written correspondence and/or change orders as approved by Prior Lake.8.0 6.0 8.0 2.0 24 $4,750 4.5 Perform part-time construction observation; document with field reports. 16.0 6.0 64.0 86 $14,320 4.6 Attend final inspections. Prepare and administer punch list(s) and follow up inspection(s) to enforce adequate and timely completion of the project.4.0 6.0 6.0 16 $3,110 4.7 Prepare all contractors pay requests and recommendations. 6.0 1.0 7 $1,339 4.8 Prepare and submit record (as-built) drawings in an approved electronic format within three months of construction completion.1.0 4.0 5 $748 Task 4 - Total WSB Staff Estimated Hours and Total Phase Fee 40.0 33.0 97.0 7.0 177 $31,742 52.0 58.0 141.0 15.5 267 $264.00 $194.00 $133.00 $135.00 2026 Hourly Billing Rate (Construction & Inspection Services) *$280.00 $206.00 $141.00 $143.00 $46,760 Filter Media Replacment Proposed Estimate of Hours and Fees Design, Bidding, and Construction Services City of Prior Lake, Minnesota Total Proposed Fee 2025 Hourly Billing Rate (Preliminary Design through Design Bidding) * Total Estimated Hours C:\Users\snelson\Downloads\PRIOR LAKE WTP Filter Media Replacment Services Proposed Fees_SGN